Contract C2, located in New Haven, included the reconstruction of approximately 1.0 miles of I-95 from western project limit just east of Stiles Street in New Haven to the eastern project limit at the New Haven/East Haven town line. The project included the reconfiguration of Interchange 49 and Interchange 50 into a single interchange accessed by a connector road between Stiles Street and Woodward Avenue.
The completed reconstruction accommodates five travel lanes in each direction from the western project limit to the reconfigured Stiles/Woodward Interchange, and from that point four travel lanes to the eastern project limit. Full shoulders and a new median barrier are also provided throughout the project. Replacement of five bridges, construction of retaining walls, new drainage systems, signing and lighting were also included.
|