| Last Updated: |
September 10, 2007 |
Project Name, Contract Number: |
Contract B, State Project No. 92-532 |
| Project Area: |
Pearl Harbor Memorial Bridge |
| Project Scope: |
Contract B is located in New Haven and consists of the replacement of the existing Pearl Harbor Memorial Bridge (a.k.a. Q-Bridge) with a new extradosed 10 lane signature bridge. The project encompasses approximately 1,300 meters (0.8 miles) of I-95 from the western project limit at the abutment at East Street and Hamilton Street to the eastern project limit at the Stiles Street abutment. Five travel lanes will be provided in each direction from the bridges west approach to a reconfigured/combined Woodward Avenue/Stiles Street interchange at the east approach. The new Pearl Harbor Memorial Bridge will be extended to include the Stiles Street overpass. Full shoulders, a new median barrier, drainage, signing, and lighting will be provided throughout the project. |
| Project Designer: |
URS Corporation |
| Project Contractor: |
TBD |
| Contract Milestones |
| Contract Milestone | Anticipated Date |
| Re-advertise | TBD | | Award | TBD | | Begin Construction | TBD | | Finish Construction | TBD |
|
| Progress Summary: |
Contract B was advertised by the Connecticut Department of Transportation (ConnDOT) on May 24, 2006.
A MANDATORY Pre-Bid Conference was held July 20, 2006 at ConnDOT in Newington, CT. |
|
|
|
 |
|
 |
|