| Last Updated: |
September 10, 2007 |
Project Name, Contract Number: |
Contract C2, State Project Nos. 92-569/92-533 |
| Project Area: |
I-95 / Fulton Terrace to Frontage Road |
| Project Scope: |
Contract C2 is located in New Haven and consists of the reconstruction of approximately 1,500 meters (1.0 mile) of I-95 from the western project limit just east of Stiles Street in New Haven to the eastern project limit at the New Haven/East Haven town line. The project includes the reconfiguration of Interchange 49 and Interchange 50 into a single interchange accessed by a connector road between Stiles Street and Woodward Avenue. The reconstruction can accommodate five travel lanes in each direction from the western project limit to the reconfigured Stiles/Woodward Interchange, and from that point four travel lanes to the eastern project limit. Full shoulders and a new median barrier will be provided throughout the project. Replacement/rehabilitation of five bridges, construction of retaining walls, new drainage systems, signing and lighting will also be included. |
| Project Designer: |
URS Corporation / Close, Jensen & Miller |
| Project Contractor: |
O & G Industries, Inc. |
| Contract Milestones |
| Contract Milestone | Anticipated Date |
| Design Completion | March 23, 2005 | | Re-advertise | May 4, 2005 | | Bid | July 13, 2005 | | Award | September 8, 2005 | | Begin Construction | September 26, 2005 | | Finish Construction | June 30, 2009 |
|
| Progress Summary: |
Work over the past month included the following:
Completed
- Pavement restoration within the New Haven Terminal for Trunkline 2.
- Construction of Wall 103.
- Wingwalls 1A/1B and 2A/2B in-between the I-95 SB and Ramp S-1 Bridges over Fulton Terrace.
- RWA and AT&T utility relocations at the Townsend Avenue Bridge over I-95 along with Stage 2 superstructure demolition.
Continued
- Demolition of the New Haven Terminal Building on Waterfront Street.
- Stage 2B NB & 4A/4B SB roadway construction along I-95 in the vicinity of Fulton Terrace.
- Installation of traffic signal mast arms.
Commenced
- Installation of Junction Chambers B and C for Trunkline 2 on Waterfront Street.
- Installation of illumination in the vicinity of Wall 103.
- Construction of temporary Ramp S-A to I-95 SB.
- Soil nailing for the final section of Wall 103 adjacent to the Townsend Avenue Bridge over I-95.
- Stage 2 substructure demolition at the Townsend Avenue Bridge over I-95.
Construction of Contract C2 is approximately 82% physically complete. |