Contract C2 - Status Report
Last Updated: September 10, 2007
Project Name,
Contract Number:
Contract C2, State Project Nos. 92-569/92-533
Project Area: I-95 / Fulton Terrace to Frontage Road
Project Scope: Contract C2 is located in New Haven and consists of the reconstruction of approximately 1,500 meters (1.0 mile) of I-95 from the western project limit just east of Stiles Street in New Haven to the eastern project limit at the New Haven/East Haven town line.
The project includes the reconfiguration of Interchange 49 and Interchange 50 into a single interchange accessed by a connector road between Stiles Street and Woodward Avenue. The reconstruction can accommodate five travel lanes in each direction from the western project limit to the reconfigured Stiles/Woodward Interchange, and from that point four travel lanes to the eastern project limit. Full shoulders and a new median barrier will be provided throughout the project. Replacement/rehabilitation of five bridges, construction of retaining walls, new drainage systems, signing and lighting will also be included.
Project Designer: URS Corporation / Close, Jensen & Miller
Project Contractor: O & G Industries, Inc.
Contract Milestones
Contract MilestoneAnticipated Date
Design CompletionMarch 23, 2005
Re-advertiseMay 4, 2005
BidJuly 13, 2005
AwardSeptember 8, 2005
Begin ConstructionSeptember 26, 2005
Finish ConstructionJune 30, 2009
Progress Summary: Work over the past month included the following:

Completed

- Pavement restoration within the New Haven Terminal for Trunkline 2.

- Construction of Wall 103.

- Wingwalls 1A/1B and 2A/2B in-between the I-95 SB and Ramp S-1 Bridges over Fulton Terrace.

- RWA and AT&T utility relocations at the Townsend Avenue Bridge over I-95 along with Stage 2 superstructure demolition.

Continued

- Demolition of the New Haven Terminal Building on Waterfront Street.

- Stage 2B NB & 4A/4B SB roadway construction along I-95 in the vicinity of Fulton Terrace.

- Installation of traffic signal mast arms.

Commenced

- Installation of Junction Chambers B and C for Trunkline 2 on Waterfront Street.

- Installation of illumination in the vicinity of Wall 103.

- Construction of temporary Ramp S-A to I-95 SB.

- Soil nailing for the final section of Wall 103 adjacent to the Townsend Avenue Bridge over I-95.

- Stage 2 substructure demolition at the Townsend Avenue Bridge over I-95.

Construction of Contract C2 is approximately 82% physically complete.