| Last Updated: |
September 10, 2007 |
Project Name, Contract Number: |
Contract E1, State Project 92-581 |
| Project Area: |
I-91/I-95/Rt. 34 Interchange |
| Project Scope: |
Contract E1 is located in and adjacent to the I-95/I-91/Route 34 Interchange in New Haven and consists of construction of soil preloading in advance of the reconstruction in Contract E. Monitoring of the soil settlement and drainage and utility relocations required to complete the soil preloading is included. Contract E1 also includes test piles, pile load tests and vibration and settlement monitoring at the Cowles Building. Test and monitoring data will be used in Contract E. |
| Project Designer: |
H.W. Lochner |
| Project Contractor: |
L. G. DeFelice, Inc. |
| Contract Milestones |
| Contract Milestone | Anticipated Date |
| Design Completion | April 28, 2004 | | Re-advertise | May 26, 2004 | | Bid | August 4, 2004 | | Award | November 1, 2004 | | Begin Construction | November 12, 2004 | | Finish Construction | December 15, 2006 |
|
| Progress Summary: |
Construction of Contract E1 is approximately 99% physically complete. |